Design Assurance Plan

Key Points

A Design Assurance Plan is created by the supplier to demonstrate how their design requirements support the achievement of Kasai UK design targets.

Minimum Content Requirements

The supplier shall identify the design assurance items required to satisfy Kasai UK design requirements.
Based on these items, the supplier shall create a design assurance plan which meets the Project / Programme schedule provided by Nissan.
These items should include

  1. Clarification of novelty (destination, structure, material, etc.)
  2. Plan of Design validation/ verification (performance / durability verification), and dates of submission of the result to Kasai UK
  3. Creation of FMEA, FTA , QFD, etc.
  4. Implementation of reliability trial
  5. Date of completion / submission of Detail Design Specifications / Drawing (3D Data, Proposal Drawing)
  6. Decision timing for Tier 2&3 sub supplier selection and CSCC completion
  7. Prototype Trial timing and material receipt dates (MRD) at Kasai UK
  8. Dates of both Supplier Internal Design Reviews and Joint Design Reviews with Nissan
  9. Plan of all Simultaneous Engineering Activities, i.e. Simultaneous part and process development
  10. Overall Tooling Timing schedule
  11. Other relevant information

For rules related to document submission, refer to the Submission Rules page.

 