DOCUMENT COMPLETION INSTRUCTION
Design Change Request

Key Points

The Design Change Request is the document used by the supplier to request Kasai UK agreement to proceed with formal drawing submission

Minimum Content Requirements

The supplier shall provide all necessary information to describe and justify the change. This shall include:

  • The reason for the change request (justification of the change)
  • A full explanation of the change, complete with a list of associated parts.
  • A full explanation of the effects of the change on the associated parts
  • A risk analysis and plan to manage all potential risks identified
  • Complete timing plan, including the anticipated first shipment date
  • The cost effect of the change.
A Design Change Request document shall only be submitted for design changes which are initiated by the supplier.