3.2 Project Planning and Production Preparation Monitoring
Activity Purpose:
Plan the project activities in line with Kasai UK
milestones
and monitor the progress.
Notes:
The tier 1 supplier shall deploy all Project Planning and Production Preparation Monitoring requirements to all sub-suppliers.
Phase
1
2
3
4
5
Activity Content
-Plan and monitor the required
KSPQP
activities.
-Ensure targets for each activity and
milestone
are included in the plans.
-Create the initial plans as required.
-Finalize and submit required plans.
-Update the plans if necessary
-Monitor progress to plans and report status.
-Review and update the plan as required.
Output Document
-
Supplier Master Schedule (Including Details)
-
Supplier Production Preparation Monitoring Plan / Status Report (plan)
-
Production Capacity Plan
-
Supplier Production Preparation Monitoring Plan / Status Report (status report)